Families need affordable electricity and cleaner power. Getting there requires a permitting system that can deliver essential grid improvements while protecting the communities expected to host them. Moms Across America supports permitting reform that serves both goals.

On November 19, 2026, the U.S. Senate passed the Bipartisan American Affordability and Jobs Act by 62-33. The legislation would speed federal approvals for energy and infrastructure projects. It also includes measures to improve grid connections and requirements intended to prevent data center electricity costs from falling on other customers. Those provisions are certainly worth keeping.

But the package also weakens certain clean water protections and makes flawed or incomplete environmental approvals harder to challenge. Changes to historic preservation review raise additional concerns about meaningful consultation in the protection of tribal and culturally significant sites.

Supporters say the bill could lower costs and create more jobs, yet it is doing so by weakening certain environmental safeguards and restricting our rights to challenge these projects legally. Is that a price we, the people, are willing to pay with our land, water, air, money, and peace of mind?

Breaking It Down

Several provisions within the Bipartisan American Affordability and Jobs Act would change how infrastructure projects are reviewed and permitted, and how communities can challenge their approval. We are asking the House to revise the following sections to protect public health and preserve communities’ right to have a meaningful say in the projects that affect them.

Sections 1102 and 1105: Fewer federal environmental reviews

Would let more projects proceed without a separate federal environmental study under the National Environmental Policy Act (NEPA). Agencies could accept qualifying state or tribal reviews instead.

The concern: A replacement review could leave important environmental questions unanswered or provide fewer opportunities for public participation. State and tribal reviews can offer strong protections; clear standards for accepting them matter.

What we need: Require comparable environmental analysis and public participation before accepting a substitute review, with additional study wherever important gaps remain.

Section 1110: Harder to challenge approvals

Generally gives communities 150 days to challenge flawed NEPA reviews. In applicable cases, challengers must have raised their concerns during public comment. Courts could not stop construction solely because the review was flawed.

The concern: Winning a legal challenge may offer little protection if construction has already caused irreversible damage.

What we need: Give communities enough time after meaningful public notice to prepare challenges. Preserve judges’ discretion to pause construction when the usual legal standards for preventing irreparable harm are met.

Section 1202: Limits of state and tribal water protections

Makes it harder for states and tribes to deny water quality approval or impose protective conditions. Those conditions would require clear and convincing evidence and must be the least burdensome way to meet water quality rules.

The concern: These added legal hurdles could make necessary water protections harder to impose or defend.

What we need: Preserve state and tribal authority to require scientifically supported safeguards without imposing a higher burden of proof on officials seeking to protect water.

Section 1203: Longer pollution permits

Allows certain wastewater discharge permits to last up to ten years instead of five, extending the time between routine renewals.

The concern: Longer permit terms could delay regular scrutiny as water conditions change or new scientific evidence emerges.

What we need: Retain five year renewals and require earlier updates when new evidence shows existing protections are inadequate.

Section 1204: Easier wetlands permitting

Under general permit rules, it treats discharges of dredged material or fill into less than two acres of protected waters as having minimal environmental effects. Limits EPA’s specified veto authority to the period between a complete application and permit issuance.

The concern: Acreage alone does not establish ecological harm, and many small wetland losses can add up to significant damage.

What we need: Assess actual wetland functions and cumulative impacts before classifying harm as minimal. Preserve EPA’s ability to address serious risks discovered after approval.

Section 1401: Harder to revisit approvals

Restricts agencies from changing or withdrawing approvals for fully permitted projects. Exceptions remain for actions authorized by law and certain urgent dangers revealed by new information.

The concern: Added procedural hurdles could delay responses to emerging risks, even where agencies retain legal authority to act.

What we need: Clearly preserve agencies’ authority to update or suspend permits when credible new health or environmental evidence warrants action, with fair notice and review.

Section 2107: Data center electricity costs

Bars utilities from passing covered additional electricity costs from newly connecting data centers to other customers and requires financial guarantees. Earlier state approved agreements generally remain, although states may revise them where their laws allow.

What needs strengthening: These protections are worth keeping. Their effectiveness depends on accurately assigning shared infrastructure costs and enforcing payment obligations. Earlier agreements also deserve scrutiny, as most data centers are covering only 38% of energy costs, leaving 62% to their neighbors, to us, to pay.

What we need: Require transparent cost calculations backed by independent audits. Review earlier agreements where state law permits, and verify that required financial guarantees adequately protect other customers.

Section 2301: Historic preservation and consultation

Limits which projects and impacts undergo historic-preservation review and sets deadlines for gathering input.

The concern: Rushed or incomplete review could allow damage to culturally significant places that later consultation cannot undo.

What we need: Preserve broad protections for significant places and allow sufficient time for meaningful tribal consultation before irreversible work begins.

What This Means On The Ground

Cleaner power and a stronger grid can bring real health benefits. A 2024 Department of Energy analysis estimated that expanded transmission could prevent 4,500-6,800 premature deaths through 2050 by reducing air pollution, compared with restricted grid expansion. Those estimates came from modeled scenarios, but they show why improving the grid deserves serious attention. A separate 2024 DOE report cited an estimate that 70 percent of transmission lines were over 25 years old, underscoring the importance of modernizing our national infrastructure.

But how we meet rising electricity demand and infrastructure upgrades matters. Burning coal to generate electricity releases mercury into the air. The EPA identifies mercury as a threat to children’s developing nervous systems and links power plant air pollution to asthma and heart disease. Coal ash, the waste left behind after coal is burned, can contain arsenic and mercury that contaminate groundwater if poorly managed. Protecting families from toxic exposures belongs in energy policy just as firmly as it belongs in our food supply.

For communities facing data centers, that means examining the supporting power infrastructure alongside the facilities themselves. Residents need to understand how connected projects could affect local water supplies and nearby farmland. Protecting wetlands helps safeguard water quality and reduce flooding around farms and homes.

Communities concerned about cell towers should examine how changes to federal environmental and historic preservation reviews could affect qualifying projects. The bill’s separate broadband exemption covers certain wired networks, including fiber.

Families need clear information before construction starts and a meaningful opportunity to influence decisions. Getting cleaner power built should go hand in hand with protecting the people who are paying for and living beside that infrastructure.

FYI—Paying For Electricity Doesn’t Remedy The Situation

Requiring data centers to pay the infrastructure costs they create is an important step toward keeping those costs off families’ electricity bills. And the research shows why those requirements need more teeth.

In a recent study published on November 9, 2026, in Nature Energy, Cornell researchers estimated that data centers were allocated only 38 percent of the infrastructure costs attributed to their growth across four U.S. grid regions in 2025. The remaining $5.13 billion was allocated largely to residents.

An October 2026 Senate investigation identified a similar situation: companies’ promises to pay their own costs focused primarily on infrastructure built exclusively for them. Tech companies and developers are disputing responsibility for broader grid upgrades triggered by their demand, arguing those costs should be shared with other customers.

Thankfully, Section 2107 of the Bipartisan American Affordability and Jobs Act would prohibit utilities from passing covered additional electricity costs from newly connecting data centers to other customers and require financial assurances for needed infrastructure. It would also direct the Federal Energy Regulatory Commission (FERC) to revise transmission pricing rules so covered data center customers are charged for the additional costs of serving them.

Individual states have already been taking action on this issue. Nine states have enacted laws in 2026 to protect electricity customers from data center costs, according to a November 2026 report from the National Conference of State Legislatures. They include New Jersey’s Data Center Fair Share law (A796/S731) and Florida’s SB 484, both of which require electricity pricing rules designed to keep other customers from subsidizing large data centers.

But state protections alone cannot fully address interstate cost shifting because state laws cannot, on their own, rewrite federally regulated transmission rates—which makes Section 2107’s federal pricing requirements particularly important.

Interstate cost shifting is when regional grid rules can “inadvertently” spread the cost of upgrades needed for data centers in one state onto electricity customers in another. The Cornell study noted that New Jersey residents, who are supposedly now protected under the Data Center Fair Share law, are helping to pay for grid upgrades linked to data center growth in Virginia. That finding makes a strong case for keeping and enforcing this new bill’s protections. We need regulators to identify the shared upgrade costs attributable to these facilities and verify that those amounts stay off other customers’ bills.

But even then, paying for power does not make pollution acceptable or replenish a strained water supply. Nor does it give the people living nearby a meaningful say in what gets built. Financial responsibility must come with enforceable protections for our health and environment.

What Happens Next

The Bipartisan American Affordability and Jobs Act still needs House approval, giving Americans an opportunity to demand stronger protections before it becomes law. Congress can improve the permitting process while protecting the communities affected by these projects.

Sign Moms Across America’s petition urging the House to strengthen environmental safeguards and preserve communities’ ability to challenge unlawful approvals before passing the Bipartisan American Affordability and Jobs Act, H.R. 2347 as amended.

Visit the Moms Across America Data Center Action page for more information and resources to help you take action. Share the petition with your neighbors so more families can make their voices heard.

Our health and our right to have a say are worth more than a faster construction schedule. Congress needs to hear that from us now.